Dashboard/SCDISC-91
SCDISC-91Unknown

[โปรชุดเซท] หน้า Order การคำนวณใน BO ของส่วนลดแสดงไม่ถูกต้อง

Jira Status: Unknown

Planned Start: 2026-03-19
Planned End: 2026-03-27

Total Delays

1

Days Delayed

3d

Total Events

10

Event Timeline

Stage TransitionTesting/QA20 Mar 2026 15:15

DevelopingTesting/QA

Status: "Developing" → "Testing/QA"

by jira_sync · jira

Date ShiftedUnknown18 Mar 2026 15:28

2026-04-152026-03-27

Field "Project target" changed

by jira_sync · jira

Date ShiftedUnknown+3d18 Mar 2026 15:28

2026-03-162026-03-19

Field "Project start" changed

by jira_sync · jira

Date ShiftedUnknown18 Mar 2026 11:49

2026-09-302026-03-16

Field "Project start" changed

by jira_sync · jira

Date ShiftedUnknown18 Mar 2026 11:49

2026-09-302026-04-15

Field "Project target" changed

by jira_sync · jira

Date ShiftedUnknown18 Mar 2026 11:47

Field "Project target" changed

by jira_sync · jira

Date ShiftedUnknown18 Mar 2026 11:47

Field "Project start" changed

by jira_sync · jira

Stage TransitionDeveloping18 Mar 2026 11:08

DesignDeveloping

Status: "Design" → "Developing"

by jira_sync · jira

Stage TransitionDesign18 Mar 2026 11:08

Features ImpactDesign

Status: "Features Impact" → "Design"

by jira_sync · jira

Stage TransitionFeatures Impact18 Mar 2026 11:08

Parking lotFeatures Impact

Status: "Parking lot" → "Features Impact"

by jira_sync · jira

Meeting Log

No meetings linked yet.