Dashboard/SCDISC-85
SCDISC-85DiscoveryM

[CO] Display Co ใน Shop app และ Sale App

Jira Status: Discovery

Planned Start: 2026-07-01
Planned End: 2026-08-31

Total Delays

26

Days Delayed

437d

Total Events

46

Event Timeline

Date ShiftedDiscovery+16d30 Jun 2026 14:40

2026-06-232026-07-15

Field "DevelopStart" changed

by jira_sync · jira

Date ShiftedDiscovery+15d30 Jun 2026 14:40

2026-06-162026-07-07

Field "Design start" changed

by jira_sync · jira

Date ShiftedDiscovery+5d30 Jun 2026 14:40

2026-06-092026-06-16

Field "Design start" changed

by jira_sync · jira

Date ShiftedDiscovery+76d30 Jun 2026 01:14

2026-04-162026-07-31

Field "Project start" changed

by jira_sync · jira

Date ShiftedDiscovery30 Jun 2026 01:14

2026-04-212026-04-16

Field "Project start" changed

by jira_sync · jira

Date ShiftedDiscovery+21d30 Jun 2026 01:14

2026-07-312026-08-31

Field "Project target" changed

by jira_sync · jira

Date ShiftedDiscovery29 Jun 2026 15:09

Field "duedate" changed

by jira_sync · jira

label_changedDiscovery29 Jun 2026 15:09

labels: "" → "track-co"

by jira_sync · jira

Date ShiftedDiscovery+7d20 May 2026 11:49

2026-04-102026-04-21

Field "DiscoveryStart" changed

by jira_sync · jira

Date ShiftedDiscovery+7d20 May 2026 11:49

2026-04-102026-04-21

Field "Project start" changed

by jira_sync · jira

Date ShiftedDiscovery20 May 2026 11:49

2026-04-302026-04-10

Field "Project start" changed

by jira_sync · jira

Date ShiftedDiscovery+10d20 May 2026 11:49

2026-04-162026-04-30

Field "Project start" changed

by jira_sync · jira

Date ShiftedDiscovery+12d20 May 2026 11:47

2026-07-152026-07-31

Field "Project target" changed

by jira_sync · jira

Date ShiftedDiscovery20 May 2026 11:47

2026-07-312026-07-15

Field "Project target" changed

by jira_sync · jira

Date ShiftedDiscovery20 May 2026 11:47

2026-05-312026-04-16

Field "Project start" changed

by jira_sync · jira

Date ShiftedDiscovery+32d20 May 2026 11:47

2026-04-162026-05-31

Field "Project start" changed

by jira_sync · jira

Date ShiftedDiscovery+12d20 May 2026 11:47

2026-07-152026-07-31

Field "Project target" changed

by jira_sync · jira

Date ShiftedDiscovery20 May 2026 11:47

2026-07-312026-07-15

Field "Project target" changed

by jira_sync · jira

Date ShiftedDiscovery+12d20 May 2026 11:46

2026-07-152026-07-31

Field "Project target" changed

by jira_sync · jira

Date ShiftedDiscovery20 May 2026 11:46

2026-07-312026-07-15

Field "Project target" changed

by jira_sync · jira

Date ShiftedDiscovery20 May 2026 11:45

Field "DevelopStart" changed

by jira_sync · jira

Date ShiftedDiscovery+23d20 May 2026 11:42

2026-06-302026-07-31

Field "Project target" changed

by jira_sync · jira

Date ShiftedDiscovery20 May 2026 11:41

Field "DevelopStart" changed

by jira_sync · jira

Date ShiftedDiscovery+35d20 May 2026 11:41

2026-04-212026-06-09

Field "Design start" changed

by jira_sync · jira

Date ShiftedDiscovery+21d13 May 2026 08:27

2026-05-312026-06-30

Field "Project target" changed

by jira_sync · jira

Date ShiftedDiscovery+23d13 May 2026 08:27

2026-03-162026-04-16

Field "Project start" changed

by jira_sync · jira

Date ShiftedDiscovery+1d12 May 2026 15:58

2026-05-292026-05-31

Field "Project target" changed

by jira_sync · jira

Date ShiftedDiscovery+10d01 Apr 2026 19:46

2026-05-152026-05-29

Field "Project target" changed

by jira_sync · jira

Date ShiftedDiscovery+11d01 Apr 2026 19:45

2026-04-212026-05-06

Field "DevelopStart" changed

by jira_sync · jira

Date ShiftedDiscovery+13d01 Apr 2026 19:44

2026-04-022026-04-21

Field "Design start" changed

by jira_sync · jira

Date ShiftedDiscovery+14d01 Apr 2026 19:44

2026-03-232026-04-10

Field "DiscoveryStart" changed

by jira_sync · jira

Date ShiftedDiscovery+2d26 Mar 2026 14:04

2026-03-312026-04-02

Field "Design start" changed

by jira_sync · jira

Date ShiftedDiscovery+11d18 Mar 2026 15:58

2026-04-302026-05-15

Field "Project target" changed

by jira_sync · jira

Date ShiftedDiscovery18 Mar 2026 15:58

2026-05-152026-04-30

Field "Project target" changed

by jira_sync · jira

Date ShiftedDiscovery+22d18 Mar 2026 15:58

2026-04-152026-05-15

Field "Project target" changed

by jira_sync · jira

Date ShiftedDiscovery18 Mar 2026 15:54

Field "DevelopStart" changed

by jira_sync · jira

Date ShiftedDiscovery18 Mar 2026 15:53

Field "Design start" changed

by jira_sync · jira

Date ShiftedDiscovery18 Mar 2026 15:53

Field "DiscoveryStart" changed

by jira_sync · jira

Date ShiftedDiscovery18 Mar 2026 15:48

2026-04-302026-04-15

Field "Project target" changed

by jira_sync · jira

Date ShiftedDiscovery18 Mar 2026 15:48

2026-04-302026-03-16

Field "Project start" changed

by jira_sync · jira

Date ShiftedDiscovery18 Mar 2026 15:48

2026-05-152026-04-30

Field "Project target" changed

by jira_sync · jira

Date ShiftedDiscovery+10d18 Mar 2026 15:48

2026-04-162026-04-30

Field "Project start" changed

by jira_sync · jira

Date ShiftedDiscovery18 Mar 2026 15:47

Field "Project target" changed

by jira_sync · jira

Date ShiftedDiscovery+16d18 Mar 2026 15:47

2026-03-252026-04-16

Field "Project start" changed

by jira_sync · jira

Date ShiftedDiscovery18 Mar 2026 14:40

Field "Project start" changed

by jira_sync · jira

Stage TransitionDiscovery18 Mar 2026 11:57

Parking lotDiscovery

Status: "Parking lot" → "Discovery"

by jira_sync · jira

Meeting Log

No meetings linked yet.