Dashboard/SCDISC-83
SCDISC-83Discovery

[CRM] Sub dealer Redeem Reward (แลกส่วนลด DC)

Jira Status: Discovery

Planned Start: 2026-08-01
Planned End: 2026-12-31

Total Delays

23

Days Delayed

474d

Total Events

39

Event Timeline

Date ShiftedDiscovery+23d20 Aug 2026 16:12

2026-11-302026-12-31

Field "Project target" changed

by jira_sync · jira

Date ShiftedDiscovery+10d20 Aug 2026 15:44

2026-11-272026-12-11

Field "UAT Date" changed

by jira_sync · jira

Date ShiftedDiscovery+20d11 Aug 2026 14:52

2026-10-312026-11-30

Field "Project target" changed

by jira_sync · jira

Date ShiftedDiscovery11 Aug 2026 14:49

2026-08-212026-08-17

Field "DiscoveryStart" changed

by jira_sync · jira

Date ShiftedDiscovery11 Aug 2026 14:41

Field "UAT Date" changed

by jira_sync · jira

Date ShiftedDiscovery11 Aug 2026 14:40

Field "DevelopStart" changed

by jira_sync · jira

Date ShiftedDiscovery11 Aug 2026 14:31

Field "Design start" changed

by jira_sync · jira

Date ShiftedDiscovery11 Aug 2026 14:30

Field "DiscoveryStart" changed

by jira_sync · jira

Stage TransitionDiscovery05 Aug 2026 09:59

Parking lotDiscovery

Status: "Parking lot" → "Discovery"

by jira_sync · jira

Date ShiftedParking lot+23d30 Jun 2026 18:05

2026-09-302026-10-31

Field "Project target" changed

by jira_sync · jira

Date ShiftedParking lot+11d30 Jun 2026 18:03

2026-09-152026-09-30

Field "Project target" changed

by jira_sync · jira

Date ShiftedParking lot+32d30 Jun 2026 18:03

2026-07-162026-08-31

Field "Project start" changed

by jira_sync · jira

Date ShiftedParking lot+21d30 Jun 2026 01:21

2026-08-152026-09-15

Field "Project target" changed

by jira_sync · jira

Date ShiftedParking lot+22d30 Jun 2026 01:21

2026-06-162026-07-16

Field "Project start" changed

by jira_sync · jira

Date ShiftedParking lot+11d08 Jun 2026 10:22

2026-07-312026-08-15

Field "Project target" changed

by jira_sync · jira

Date ShiftedParking lot13 May 2026 08:28

2026-06-302026-06-16

Field "Project start" changed

by jira_sync · jira

Date ShiftedParking lot+12d13 May 2026 08:28

2026-07-152026-07-31

Field "Project target" changed

by jira_sync · jira

Date ShiftedParking lot+11d18 Mar 2026 16:01

2026-06-302026-07-15

Field "Project target" changed

by jira_sync · jira

Date ShiftedParking lot+25d18 Mar 2026 16:01

2026-05-262026-06-30

Field "Project start" changed

by jira_sync · jira

Date ShiftedParking lot012 Mar 2026 10:49

2026-06-302026-06-30

Field "Project target" changed

by jira_sync · jira

Date ShiftedParking lot+6d12 Mar 2026 10:49

2026-05-162026-05-26

Field "Project start" changed

by jira_sync · jira

Date ShiftedParking lot12 Mar 2026 10:48

2026-06-302026-05-16

Field "Project start" changed

by jira_sync · jira

Date ShiftedParking lot+31d11 Mar 2026 18:52

2026-05-162026-06-30

Field "Project start" changed

by jira_sync · jira

Date ShiftedParking lot+11d11 Mar 2026 18:52

2026-06-152026-06-30

Field "Project target" changed

by jira_sync · jira

Date ShiftedParking lot+22d11 Mar 2026 18:33

2026-04-162026-05-16

Field "Project start" changed

by jira_sync · jira

Date ShiftedParking lot+21d11 Mar 2026 18:33

2026-05-152026-06-15

Field "Project target" changed

by jira_sync · jira

Date ShiftedParking lot11 Mar 2026 18:33

2026-06-302026-05-15

Field "Project target" changed

by jira_sync · jira

Date ShiftedParking lot11 Mar 2026 18:33

2026-06-302026-04-16

Field "Project start" changed

by jira_sync · jira

Date ShiftedParking lot+32d11 Mar 2026 16:51

2026-05-152026-06-30

Field "Project target" changed

by jira_sync · jira

Date ShiftedParking lot+53d11 Mar 2026 16:51

2026-04-162026-06-30

Field "Project start" changed

by jira_sync · jira

Date ShiftedParking lot+11d11 Mar 2026 16:50

2026-04-302026-05-15

Field "Project target" changed

by jira_sync · jira

Date ShiftedParking lot11 Mar 2026 16:50

2026-05-312026-04-16

Field "Project start" changed

by jira_sync · jira

Date ShiftedParking lot+22d11 Mar 2026 15:27

2026-04-302026-05-31

Field "Project start" changed

by jira_sync · jira

Date ShiftedParking lot+11d11 Mar 2026 15:27

2026-04-152026-04-30

Field "Project target" changed

by jira_sync · jira

Date ShiftedParking lot+33d11 Mar 2026 15:27

2026-03-162026-04-30

Field "Project start" changed

by jira_sync · jira

Date ShiftedParking lot11 Mar 2026 15:14

2026-04-302026-03-16

Field "Project start" changed

by jira_sync · jira

Date ShiftedParking lot11 Mar 2026 15:14

2026-04-302026-04-15

Field "Project target" changed

by jira_sync · jira

Date ShiftedParking lot11 Mar 2026 15:14

Field "Project target" changed

by jira_sync · jira

Date ShiftedParking lot11 Mar 2026 15:14

Field "Project start" changed

by jira_sync · jira

Meeting Log

No meetings linked yet.