Dashboard/SCDISC-67
SCDISC-67Parking lotXL

Advance Promotion eg, Flash sale

Jira Status: Parking lot

Planned Start: 2026-05-16
Planned End: 2026-09-30

Total Delays

14

Days Delayed

330d

Total Events

55

Event Timeline

Date ShiftedParking lot+34d13 May 2026 08:15

2026-04-012026-05-19

Field "DiscoveryStart" changed

by jira_sync · jira

Date ShiftedParking lot+22d13 May 2026 08:15

2026-08-312026-09-30

Field "Project target" changed

by jira_sync · jira

Date ShiftedParking lot+21d13 May 2026 08:15

2026-07-312026-08-31

Field "Project target" changed

by jira_sync · jira

Date ShiftedParking lot13 May 2026 08:15

2026-05-182026-05-16

Field "Project start" changed

by jira_sync · jira

Date ShiftedParking lot13 May 2026 08:14

2026-09-302026-07-31

Field "Project target" changed

by jira_sync · jira

Date ShiftedParking lot013 May 2026 08:14

2026-05-162026-05-18

Field "Project start" changed

by jira_sync · jira

Date ShiftedParking lot13 May 2026 08:14

2026-05-312026-05-16

Field "Project start" changed

by jira_sync · jira

Date ShiftedParking lot+11d13 May 2026 08:14

2026-09-152026-09-30

Field "Project target" changed

by jira_sync · jira

Date ShiftedParking lot18 Mar 2026 16:02

2026-10-152026-09-15

Field "Project target" changed

by jira_sync · jira

Date ShiftedParking lot18 Mar 2026 16:02

2026-06-302026-05-31

Field "Project start" changed

by jira_sync · jira

Date ShiftedParking lot+33d18 Mar 2026 16:02

2026-08-312026-10-15

Field "Project target" changed

by jira_sync · jira

Date ShiftedParking lot+53d18 Mar 2026 16:02

2026-04-162026-06-30

Field "Project start" changed

by jira_sync · jira

Date ShiftedParking lot+10d13 Mar 2026 12:09

2026-08-152026-08-31

Field "Project target" changed

by jira_sync · jira

Date ShiftedParking lot+11d13 Mar 2026 12:09

2026-04-012026-04-16

Field "Project start" changed

by jira_sync · jira

Date ShiftedParking lot12 Mar 2026 12:16

Field "DiscoveryStart" changed

by jira_sync · jira

Date ShiftedParking lot12 Mar 2026 12:16

2026-05-312026-04-01

Field "Project start" changed

by jira_sync · jira

Stage TransitionParking lot12 Mar 2026 12:01

Release (DONE)Parking lot

Status: "Release (DONE)" → "Parking lot"

by jira_sync · jira

Stage TransitionRelease (DONE)12 Mar 2026 11:44

UAT(STH)Release (DONE)

Status: "UAT(STH)" → "Release (DONE)"

by jira_sync · jira

Stage TransitionUAT(STH)12 Mar 2026 11:44

Release (DONE)UAT(STH)

Status: "Release (DONE)" → "UAT(STH)"

by jira_sync · jira

Stage TransitionRelease (DONE)12 Mar 2026 11:43

Ready to ReleaseRelease (DONE)

Status: "Ready to Release" → "Release (DONE)"

by jira_sync · jira

Stage TransitionReady to Release12 Mar 2026 11:42

UAT(STH)Ready to Release

Status: "UAT(STH)" → "Ready to Release"

by jira_sync · jira

Stage TransitionUAT(STH)12 Mar 2026 11:42

Testing/QAUAT(STH)

Status: "Testing/QA" → "UAT(STH)"

by jira_sync · jira

Stage TransitionTesting/QA12 Mar 2026 11:41

DevelopingTesting/QA

Status: "Developing" → "Testing/QA"

by jira_sync · jira

Stage TransitionDeveloping12 Mar 2026 11:40

DesignDeveloping

Status: "Design" → "Developing"

by jira_sync · jira

Stage TransitionDesign12 Mar 2026 11:40

Features ImpactDesign

Status: "Features Impact" → "Design"

by jira_sync · jira

Stage TransitionFeatures Impact12 Mar 2026 11:40

UAT(STH)Features Impact

Status: "UAT(STH)" → "Features Impact"

by jira_sync · jira

Stage TransitionUAT(STH)12 Mar 2026 11:39

Parking lotUAT(STH)

Status: "Parking lot" → "UAT(STH)"

by jira_sync · jira

Stage TransitionParking lot12 Mar 2026 11:39

Features ImpactParking lot

Status: "Features Impact" → "Parking lot"

by jira_sync · jira

Stage TransitionFeatures Impact12 Mar 2026 11:37

Parking lotFeatures Impact

Status: "Parking lot" → "Features Impact"

by jira_sync · jira

Stage TransitionParking lot12 Mar 2026 11:37

Features ImpactParking lot

Status: "Features Impact" → "Parking lot"

by jira_sync · jira

Stage TransitionFeatures Impact12 Mar 2026 11:35

DiscoveryFeatures Impact

Status: "Discovery" → "Features Impact"

by jira_sync · jira

Stage TransitionDiscovery12 Mar 2026 11:35

Parking lotDiscovery

Status: "Parking lot" → "Discovery"

by jira_sync · jira

Stage TransitionParking lot12 Mar 2026 11:35

DiscoveryParking lot

Status: "Discovery" → "Parking lot"

by jira_sync · jira

Stage TransitionDiscovery12 Mar 2026 11:33

Parking lotDiscovery

Status: "Parking lot" → "Discovery"

by jira_sync · jira

Stage TransitionParking lot12 Mar 2026 11:29

DiscoveryParking lot

Status: "Discovery" → "Parking lot"

by jira_sync · jira

Stage TransitionDiscovery12 Mar 2026 11:23

Parking lotDiscovery

Status: "Parking lot" → "Discovery"

by jira_sync · jira

Stage TransitionParking lot12 Mar 2026 11:22

DiscoveryParking lot

Status: "Discovery" → "Parking lot"

by jira_sync · jira

Stage TransitionDiscovery12 Mar 2026 11:21

Parking lotDiscovery

Status: "Parking lot" → "Discovery"

by jira_sync · jira

Stage TransitionParking lot12 Mar 2026 11:16

DiscoveryParking lot

Status: "Discovery" → "Parking lot"

by jira_sync · jira

Stage TransitionDiscovery12 Mar 2026 11:14

Parking lotDiscovery

Status: "Parking lot" → "Discovery"

by jira_sync · jira

Stage TransitionParking lot12 Mar 2026 11:14

DiscoveryParking lot

Status: "Discovery" → "Parking lot"

by jira_sync · jira

Stage TransitionDiscovery12 Mar 2026 11:12

Parking lotDiscovery

Status: "Parking lot" → "Discovery"

by jira_sync · jira

Date ShiftedParking lot+34d11 Mar 2026 18:51

2026-06-302026-08-15

Field "Project target" changed

by jira_sync · jira

Date ShiftedParking lot+44d11 Mar 2026 18:51

2026-03-312026-05-31

Field "Project start" changed

by jira_sync · jira

Date ShiftedParking lot011 Mar 2026 16:59

2026-06-302026-06-30

Field "Project target" changed

by jira_sync · jira

Date ShiftedParking lot11 Mar 2026 16:59

2026-07-312026-06-30

Field "Project target" changed

by jira_sync · jira

Date ShiftedParking lot11 Mar 2026 16:59

2026-04-162026-03-31

Field "Project start" changed

by jira_sync · jira

Date ShiftedParking lot11 Mar 2026 14:56

2026-04-302026-04-16

Field "Project start" changed

by jira_sync · jira

Date ShiftedParking lot+12d11 Mar 2026 14:56

2026-07-152026-07-31

Field "Project target" changed

by jira_sync · jira

Date ShiftedParking lot+10d11 Mar 2026 14:56

2026-04-162026-04-30

Field "Project start" changed

by jira_sync · jira

Date ShiftedParking lot11 Mar 2026 14:56

2026-07-312026-07-15

Field "Project target" changed

by jira_sync · jira

Date ShiftedParking lot+12d11 Mar 2026 14:54

2026-03-312026-04-16

Field "Project start" changed

by jira_sync · jira

Date ShiftedParking lot+23d11 Mar 2026 14:54

2026-06-302026-07-31

Field "Project target" changed

by jira_sync · jira

Date ShiftedParking lot11 Mar 2026 13:45

Field "Project target" changed

by jira_sync · jira

Date ShiftedParking lot11 Mar 2026 13:45

Field "Project start" changed

by jira_sync · jira

Meeting Log

No meetings linked yet.