Order Tracking, สินค้าค้างส่ง และ การจัดส่งสินค้า
Jira Status: Testing/QA
Total Delays
9
Days Delayed
95d
Total Events
20
Event Timeline
Developing → Testing/QA
Status: "Developing" → "Testing/QA"
by jira_sync · jira
Design → Developing
Status: "Design" → "Developing"
by jira_sync · jira
2026-03-24 → 2026-03-25
Field "DevelopStart" changed
by jira_sync · jira
2026-04-10 → 2026-04-21
Field "Project target" changed
by jira_sync · jira
Field "DevelopStart" changed
by jira_sync · jira
2026-04-07 → 2026-04-10
Field "Project target" changed
by jira_sync · jira
2026-04-06 → 2026-04-07
Field "Project target" changed
by jira_sync · jira
2026-02-10 → 2026-03-10
Field "Project start" changed
by jira_sync · jira
2026-02-24 → 2026-02-10
Field "Project start" changed
by jira_sync · jira
Field "Design start" changed
by jira_sync · jira
2026-03-15 → 2026-04-06
Field "Project target" changed
by jira_sync · jira
2026-02-14 → 2026-02-24
Field "Project start" changed
by jira_sync · jira
Features Impact → Design
Status: "Features Impact" → "Design"
by jira_sync · jira
Parking lot → Features Impact
Status: "Parking lot" → "Features Impact"
by jira_sync · jira
2026-03-31 → 2026-02-14
Field "Project start" changed
by jira_sync · jira
2026-03-31 → 2026-03-15
Field "Project target" changed
by jira_sync · jira
2026-02-24 → 2026-03-31
Field "Project start" changed
by jira_sync · jira
2026-03-06 → 2026-03-31
Field "Project target" changed
by jira_sync · jira
Field "Project target" changed
by jira_sync · jira
Field "Project start" changed
by jira_sync · jira
Meeting Log