Dashboard/SCDISC-61
SCDISC-61Release (DONE)

Display Shop Credit in Sale App

Jira Status: Release (DONE)

Planned Start: 2026-02-01
Planned End: 2026-03-16

Total Delays

4

Days Delayed

50d

Total Events

16

Event Timeline

Stage TransitionRelease (DONE)23 Mar 2026 16:47

Ready to ReleaseRelease (DONE)

Status: "Ready to Release" → "Release (DONE)"

by jira_sync · jira

Date ShiftedRelease (DONE)12 Mar 2026 13:08

2026-03-312026-03-16

Field "Project target" changed

by jira_sync · jira

Stage TransitionReady to Release12 Mar 2026 13:08

UAT(STH)Ready to Release

Status: "UAT(STH)" → "Ready to Release"

by jira_sync · jira

Date ShiftedRelease (DONE)12 Mar 2026 12:21

Field "Requested Ship date" changed

by jira_sync · jira

Date ShiftedRelease (DONE)12 Mar 2026 12:21

Field "UAT Date" changed

by jira_sync · jira

Date ShiftedRelease (DONE)+11d11 Mar 2026 18:39

2026-03-162026-03-31

Field "Project target" changed

by jira_sync · jira

Date ShiftedRelease (DONE)+19d11 Mar 2026 18:39

2026-02-032026-02-28

Field "Project start" changed

by jira_sync · jira

Date ShiftedRelease (DONE)11 Mar 2026 18:17

Field "DevelopStart" changed

by jira_sync · jira

Stage TransitionUAT(STH)11 Mar 2026 17:29

Release (DONE)UAT(STH)

Status: "Release (DONE)" → "UAT(STH)"

by jira_sync · jira

Date ShiftedRelease (DONE)011 Mar 2026 16:51

2026-03-152026-03-16

Field "Project target" changed

by jira_sync · jira

Date ShiftedRelease (DONE)11 Mar 2026 16:50

2026-02-282026-02-03

Field "Project start" changed

by jira_sync · jira

Stage TransitionRelease (DONE)11 Mar 2026 15:16

Parking lotRelease (DONE)

Status: "Parking lot" → "Release (DONE)"

by jira_sync · jira

Date ShiftedRelease (DONE)+1d11 Mar 2026 15:09

2026-03-132026-03-15

Field "Project target" changed

by jira_sync · jira

Date ShiftedRelease (DONE)+19d11 Mar 2026 15:09

2026-02-032026-02-28

Field "Project start" changed

by jira_sync · jira

Date ShiftedRelease (DONE)11 Mar 2026 13:43

Field "Project target" changed

by jira_sync · jira

Date ShiftedRelease (DONE)11 Mar 2026 13:43

Field "Project start" changed

by jira_sync · jira

Meeting Log

No meetings linked yet.