Dashboard/SCDISC-59
SCDISC-59Release (DONE)

Credit Limit version 2

Jira Status: Release (DONE)

Planned Start: 2025-12-02
Planned End: 2026-03-16

Total Delays

1

Days Delayed

10d

Total Events

9

Event Timeline

Stage TransitionRelease (DONE)23 Mar 2026 16:48

Ready to ReleaseRelease (DONE)

Status: "Ready to Release" → "Release (DONE)"

by jira_sync · jira

Date ShiftedRelease (DONE)13 Mar 2026 10:40

2026-03-182026-03-10

Field "UAT Date" changed

by jira_sync · jira

Date ShiftedRelease (DONE)12 Mar 2026 11:53

Field "UAT Date" changed

by jira_sync · jira

Date ShiftedRelease (DONE)12 Mar 2026 11:22

Field "Requested Ship date" changed

by jira_sync · jira

Stage TransitionReady to Release11 Mar 2026 17:30

UAT(STH)Ready to Release

Status: "UAT(STH)" → "Ready to Release"

by jira_sync · jira

Date ShiftedRelease (DONE)+10d11 Mar 2026 16:51

2026-03-022026-03-16

Field "Project target" changed

by jira_sync · jira

Stage TransitionUAT(STH)11 Mar 2026 14:46

Parking lotUAT(STH)

Status: "Parking lot" → "UAT(STH)"

by jira_sync · jira

Date ShiftedRelease (DONE)11 Mar 2026 13:43

Field "Project target" changed

by jira_sync · jira

Date ShiftedRelease (DONE)11 Mar 2026 13:43

Field "Project start" changed

by jira_sync · jira

Meeting Log

No meetings linked yet.